SPMT bridge install

Project Location

Hull A63

Live has installed ground protection and heavy-duty access solutions for a time-critical pedestrian bridge installation to connect Hull city centre to its waterfront.

The 60-metre, 150-tonne footbridge was moved into position by SPMTs across the A63 overnight on 2 Nov. Live installed a variety of products to create a bespoke solution.

Our customer explained

The advice given to us ahead of the works was clear and concise, which helped us plan the installation. All instructions were followed impeccably by all crews involved. The road was re-opened 14 hours early on the Sunday afternoon which made the weekend a huge success

Trakway SPMT Bridge installation